Google's Belgian data center permit appeal set for Jan. 7 after construction halt

RUKUS· · 15m ← 45h
Chat

Inspectors found Google's southern Belgium data center nearly finished on November 27, with structural work complete, though requested planning-permission changes had not been approved. Wallonia authorities ordered the company to stop construction, and the regional government said it was submitting a report to prosecutors alleging illegal construction of a 3-hectare building.

Greenpeace announced expedited legal proceedings on November 28, and Google stopped work at the site.

Google had received permission in 2024 to build 3 Belgian data centers using air-based cooling. It later applied to reduce the project to 2 centers and switch to water-based cooling from the River Sambre. The amended permit was granted in April 2026, then annulled in August after a third-party appeal.

Google continued construction while challenging the annulment. Its appeal is scheduled for a Jan. 7 hearing before Belgium's Council of State.

  1. Inspectors visiting Google's southern Belgium data center found the building nearly finished, with its structural work complete, although the requested changes to its planning permission had not been approved.

    Wallonia authorities ordered Google to stop construction, giving 300 workers a verbal order that was confirmed in writing to the company.

    Wallonia's regional government was submitting a report to prosecutors alleging illegal construction of a 3-hectare building.

    Google said it was 'committed to maintaining an open and collaborative dialogue' with regional authorities.

    Wallonia spokesperson Nicolas Yernaux said the report alleged 'a major offence: the illegal construction of a building covering 3 hectares'.

  2. Greenpeace announced it was initiating expedited legal proceedings against Google's construction.

    Google stopped construction at the site.

    Google said it stopped work in accordance with local authorities' instructions and until further notice.

  3. Google received permission in 2024 to build 3 Belgian data centers using air-based cooling.

    Google applied to reduce the project to 2 data centers and switch to water-based cooling from the River Sambre; the amended permit was granted in April 2026 and annulled in August after a third-party appeal.

    Google continued construction while challenging the permit's annulment.

    Google's appeal was scheduled for a Jan. 7 hearing before Belgium's Council of State.

    Google said several other permits for the data center campus remained valid.

    Google said work since August was mainly intended to preserve and secure the site during its appeal and to carry out construction authorized under the original permit.